塑料检查井安装的准备工作从测绘开始
塑料检查井安装的准备工作从测绘开始,到检查井安稳的放到工地上,要经过3个步骤。分别是:
Preparations for the installation of plastic inspection wells begin with surveying and mapping, and go through three steps to place the inspection wells safely on the construction site. Namely:
确定方案---现场的查验---查验后摆放
Determine the plan - - site inspection - - put after inspection
确定方案
Definite plan
1、排水检查井安装施工前,会与排水管道工程同时做好技术交底工作。
1. Before the installation and construction of drainage inspection wells, the technical undertaking will be done at the same time with the drainage pipeline project.
2、 施工单位需编制详细的施工组织方案。
2. Construction units need to work out detailed construction organization plans.
3、 施工单位需根据设计文件编制“塑料排水检查井工程备料表”。
3. The construction unit shall compile the "material preparation table for plastic drainage inspection wells" according to the design documents.
4、“塑料排水检查井工程备料表”应按检查井的井位编号逐个进行填写。
4. The "Preparations Form for Plastic Drainage Inspection Wells" should be filled in one by one according to the location number of the inspection wells.
现场的查验
On-site inspection
1、 查验部件的产品质量合格证和检验报告;
1. Quality certificate and inspection report of inspection parts;
2 、查验部件的规格型号、接口管径、接管数量;
2. Check the specifications and models of components, the diameters of interfaces and the number of nozzles.
3 、查验部件的外观质量、尺寸偏差等。
3. Check the appearance quality and size deviation of components.
查验后摆放
Place after inspection
查验后的检查井部件,要按井位的编号进行有序码放。并且摆放时不要负重和挤压
The inspected well parts should be orderly coded according to the number of the well location. And don't load or squeeze when putting it in place.
1、要放在通风良好的棚内,远离热源。
1. Keep in a well-ventilated shed away from heat sources.
2、如果是露天储存,要有防晒措施。
2. If it is stored in the open air, sunscreen measures should be taken.
3、不与化学物品混放,避免腐蚀。
3. Do not mix with chemicals to avoid corrosion.